Wind Power
HNEEP-CLP Weihai Wind Farm Works

    The works locates on northern coastal line of Weihai City in Shandong Province. Its 1st-phase works has 13 wind turbines erected with unit capacity of 1500kW and a total installed capacity of 19.5MW and been put into operation. The 2nd-phase works has 33 wind turbines erected with unit capacity of 1500kW and a total installed capacity of 49.5MW and been put into operation in May, 2007. At present the 3rd-phase works are being under construction, which has a installed capacity of 49.5MW.

    Our institute completed the whole process of the 1st phase works construction covering compilation of pre-feasibility study report and feasibility study report investigation, design of construction drawings; and compilation of feasibility study report of the 2nd phase works, for which construction drawings for tendering are being designed, and feasibility study of the 3rd phase works being conducted.